Our new sign is up and standing tall! You can’t miss it from the road coming in.

The security lighting has been installed around the building and the compound.

We now have the security fencing up. Our compound is now full fenced and secure.

The siding is on and the roll-up doors are hung.

The security fencing for the property has begun and crush gravel is laid for the Boat and RV storage area.

The foundation is complete and the first floor units are framed.

The Boat and RV storage area is almost complete and ready for security fencing.

The second floor units are being framed in.

The concrete fire separation is poured on the second floor, and the units are laid out ready for framing.